No
|
Product
|
Quantity
|
Unit Price
|
Amount
|
Function
|
1 | TO SUPPLY LABOUR AND MATERIALS TO MODIFY AND INSTALL 1 LOTS NEW FABRICATE MAIN DUCT WORK . | 1.00 | 4,400.00 | 4,400.00 | Edit | Delete | | MATERIAL IN USE : PU FOAM , 6 NOS SUPPLY AND RETURN GRILL (350 x 350 ) ,FLEXIBLE DUCT .
LOCATION : FCU 02-41
| 2 | TO SUPPLY LABOUR AND MATERIALS TO MODIFY AND INSTALL 1 LOTS NEW FABRICATE MAIN DUCT WORK . | 1.00 | 3,900.00 | 3,900.00 | Edit | Delete | | MATERIAL IN USE : PU FOAM , 5 NOS SUPPLY AND RETURN GRILL (350 x 350 ) ,FLEXIBLE DUCT .
LOCATION : FCU 02-42 | 3 | DRAWING AND PE ENDORSEMENT SUBMISSION . | 1.00 | 1,200.00 | 1,200.00 | Edit | Delete | 4 | TERM OF PAYMENT : | | | | Edit | Delete | | ) 70% DEPOSIT TO ORDER AIRCON AND CONFIRM JOB.
2)) 20% PROGRESSIVE CLAIM WHEN AIRCON ARRIVE.
3) FULL PAYMENT UPON JOB COMPLETED.
4)) EXCLUSION: WORKS NOT STATED ABOVE | Total | 3.00 | | 9,500.00 |
5 |
|
|
|
|
|
|
|
|