						No
					 | 
					
						Product
					 | 
					
						Quantity
					 | 
					
						Unit Price
					 | 
					
						Amount
					 | 
					
						Function
					 | 
				 
				| 1 | TO SUPPLY LABOUR AND MATERIALS TO MODIFY AND INSTALL 1 LOTS NEW FABRICATE MAIN DUCT WORK .  | 1.00 | 4,400.00 | 4,400.00 |   Edit |   Delete |  |   |  MATERIAL IN USE : PU FOAM , 6 NOS SUPPLY AND RETURN GRILL (350 x 350 )  ,FLEXIBLE  DUCT . 
 
 LOCATION : FCU 02-41 
 
  |  | 2 | TO SUPPLY LABOUR AND MATERIALS TO MODIFY AND INSTALL 1 LOTS NEW FABRICATE MAIN DUCT WORK . | 1.00 | 3,900.00 | 3,900.00 |   Edit |   Delete |  |   | MATERIAL IN USE : PU FOAM , 5 NOS SUPPLY AND RETURN GRILL (350 x 350 ) ,FLEXIBLE DUCT .
 
 LOCATION : FCU 02-42 |  | 3 | DRAWING AND PE ENDORSEMENT SUBMISSION .  | 1.00 | 1,200.00 | 1,200.00 |   Edit |   Delete |  | 4 | TERM OF PAYMENT :  |   |   |   |   Edit |   Delete |  |   | ) 70% DEPOSIT TO ORDER AIRCON AND CONFIRM JOB.
 2)) 20% PROGRESSIVE CLAIM WHEN AIRCON ARRIVE.
 3) FULL PAYMENT UPON JOB COMPLETED.
 4)) EXCLUSION: WORKS NOT STATED ABOVE |  | Total | 3.00 |   | 9,500.00 |  				
					| 
						5					 | 
					
						
												  
						 	
					 | 	
					
											 | 
					
											 | 
					
					 | 
				 
				
				
					| 
					 | 
					
											 | 
				 
				
					| 
												  
											 | 
				 	
							 
		 |