1 | TO SUPPLY AND INSTALL TWO SETS OF NEW MITSUBISHI INVERTER ENERGY SAVING | 2.00 | 1,400.00 | 2,800.00 | Edit | Delete |
| 9K BTU SINGLE SPLIT AIRCON C/W CONCEALED NEW REFRIGERATED COPPER PIPE , PVC DRAIN PIPE AND SYSTEM CONTROL WIRING .
MODEL : MUY-GP10VF/MSY-GP10VF (9000BTU ) x 2 sets
LOCATION : LEVEL 1 (SMALL ROOM & EXTENDED ROOM ) |
2 | TO SUPPLY AND INSTALL ONE SETS OF NEW MITSUBISHI INVERTER ENERGY SAVING | 1.00 | 3,550.00 | 3,550.00 | Edit | Delete |
| MULTI SPLIT AIRCON C/W CONCEALED NEW REFRIGERATED COPPER PIPE , PVC DRAIN PIPE AND SYSTEM CONTROL WIRING .
MODEL : MXY-3H28VG-SG1 /MSXY-FP13VG-SG1(12.000btu)
LOCATION : ROOM 1 & ROOM 2 |
3 | TO SUPPLY AND INSTALL ONE SETS OF NEW MITSUBISHI INVERTER ENERGY SAVING | 1.00 | 4,380.00 | 4,380.00 | Edit | Delete |
| MULTI SPLIT AIRCON C/W CONCEALED NEW REFRIGERATED COPPER PIPE , PVC DRAIN PIPE AND SYSTEM CONTROL WIRING .
MODEL : MXY-3H28VG-SG1
MSXY-FP10VG-SG1 (9000btu) x 2 nos
MSXY - FP18VG -SG1 (18000btu) x 1 nos
LOCATION : MASTERBED ROOM , SMALL OFFICE , WARDOBES AREA |
4 |
|
|
|
|
|
|
|
5 | TO SUPPLY AND INSTALLONE SET OF NEW MITSUBISHI 24K BTU CEILING CASSETTE | 1.00 | 3,380.00 | 3,380.00 | Edit | Delete |
| C/W CONCEALED NEW REFRIGERATED COPPER PIPE , PVC DRAIN PIPE AND SYSTEM CONTROL WIRING .
MODEL : SUY-M80VA-SG / PLY-M80EA-SG
LOCATION : LIGHT KITCHEN AREA |
6 | TO SUPPLY AND INSTALL 6 NOS OF NEW STAINLESS STEEL OUTDOOR SUPPORT BRACKET . | 6.00 | 180.00 | 1,080.00 | Edit | Delete |
7 | REMARK | | | | Edit | Delete |
| NEW INSTALLATION PIPING MATERIALS AS BELOW :
- K -FLEX CLASS O INSULATION
-22 SWG COPPER PIPE
-PVC 16MM DRAINAGE PIPE
- 3C x 70 CABLE WIRE
|
8 | REMARK | | | | Edit | Delete |
| EQUIPMENT WARRANTY AS BELOW :
- FAN COIL WARRANTY - 1 YEAR ( MITSUBISHI AGENT )
- COMPRESSOR WARRANTY - 5 YEAR (MITSUBISHI AGENT )
- WORKMENSHIP - 1 YEAR ( KAILI AIRCON PTE LTD
|
9 | REMARK | | | | Edit | Delete |
| 1) 70% DEPOSIT TO ORDER AIRCON AND CONFIRM JOB.
2) 20% PROGRESSIVE CLAIM WHEN AIRCON ARRIVE.
3) 10%FULL PAYMENT UPON JOB COMPLETED.
4) EXCLUSION: WORKS NOT STATED ABOVE. |
Total | 11.00 | | 15,190.00 |