						No
					 | 
					
						Product
					 | 
					
						Quantity
					 | 
					
						Unit Price
					 | 
					
						Amount
					 | 
					
						Function
					 | 
				
											
								| 
									1								 | 
								
									
																		  
									 	
								 | 
								
																	 | 
								
																	 | 
								
								 | 
							
							
							
								| 
								 | 
								
																	 | 
							
							
								| 
																		  
																	 | 
							
	
				| 2 | TO SUPPLY AIRCON, LABOUR AND MATERIALS TO INSTALL: | 1.00 | 38,160.00 | 38,160.00 |   Edit |   Delete | 
|   | BRAND: DAIKIN VRV
 CU: RXQ22AMYM (RXQ10A+RXQ12A) FOR *PLOT 2*
 ~BASEMENT~
 A) FXFQ80A CASSETTE*2 (ENT HALL + PANTRY+ LIBRARY)
 B) FXAQ25A WALL * 1 (STORE)
 
 ~1ST STY~
 C) FXAQ40A WALL*1 (BDRM 1)
 D) FXFQ63A CASSETTE*1 + FXAQ63A WALL*1 (DINING+CORRIDOR+DRY KITCHEN)
 
 ~2ND STY~
 E) FXAQ63A WALL*1 (MASTER RM)
 F) FXAQ40A WALL*1 (JR MASTER)
 
 ~ATTIC~
 G) FXAQ32A WALL*1 (BDRM 2)
 H) FXAQ63A WALL *1 (GYM) | 
| 3 | TO SUPPLY AIRCON, LABOUR AND MATERIALS TO INSTALL: | 1.00 | 40,430.00 | 40,430.00 |   Edit |   Delete | 
|   | BRAND: DAIKIN VRV
 CU: RXQ22AMYM (RXQ10A+RXQ12A)
 ~BASEMENT~
 A) FXFQ100A CASSETTE*2 (DRY KIT+ENT HALL +LIFT LOBBY+DINING)
 B) FXAQ20A WALL*1 (STORE)
 
 ~1ST STY~
 C) FXAQ25A WALL*2 (BDRM 1 + BDRM 2)
 D) FXAQ40A WALL* 2 ( LIVING RM + CORRIDOR)
 
 ~2ND STY~
 E) FXAQ63A WALL*1 (MASTER RM)
 F) FXAQ40A WALL*1 (JR MASTER)
 
 ~ATTIC~
 G)FXAQ32A WALL *1 (BDRM 2)
 H) FXAQ50A WALL * 1 (ENTERTAINMENT)
 
 INCLUDE INSULATION MAIN PIPE 1" THK(GAS);1/2"THK (LIQUID);TO FCU 3/4" THK; 
 WATER PIPE 16MM-20MM; CABLE TRAY AND ALL NECESSARY PARTS. | 
| 4 | FRESH AIR DUCT WORK C/W IN LINE FAN (MODEL:100) AND GRILL | 2.00 | 1,200.00 | 2,400.00 |   Edit |   Delete | 
|   | MATERIALS USED: PE FOAM
 LOCATION : PLOT 2 (BASEMENT) & PLOT 3 (BASEMENT) | 
| 5 | FRESH AIR DUCT WORK C/W IN LINE FAN (MODEL:100) AND GRILL | 2.00 | 950.00 | 1,900.00 |   Edit |   Delete | 
|   | MATERIALS USED: PE FOAM
 LOCATION : PLOT 1(BASEMENT) & PLOT 2 (1ST STY) | 
| 6 | REMARKS: |   |   |   |   Edit |   Delete | 
|   | 1) EXCLUSION: STAINLESS STEEL BRACKET & MOBILE CRANE.
 2) ALL REMOTE CONTROLLER IS WIRELESS.
 3) TESTING AND COMMISSIONING INCLUDE.
 4) 30% DEPOSIT TO CONFIRM JOB AND ORDER AIRCON.
 5) PROGRESSIVE PAYMENT 80% WHILE AIRCON DELIVERY TO SITE.
 6) FULL PAYMENT UPON JOB COMPLETION.
  | 
| Total | 6.00 |   | 82,890.00 |