Kaili Aircond
Singapore


Online Billing Portal
Cloud Solutions Sdn Bhd
Vince : +6012 7040 900 ( watapps / wechat )
[email protected]

   File Attachement   Create Revised Copy
Customer Information
Branch Last Update admin   
Name Quotation No Q
Running Reference : Q19/1008
Address Customer No
Address 2
Address 3
Address 4
Contact Tel Fax
Quotation Information
Date
    
Ref
Validity Delivery Terms
Subject
Currency Remark
      
Quotation Detail Information
No Product Quantity Unit Price Amount Function
1TO SUPPLY CHILLED WATER CASSETTE UNIT ONLY6.001,550.009,300.00 Edit Delete
 43000BTU CASSETTE (WORKSTATION, PASSENGER WAY, NFR X4 )
236000BTU CASSETTE (R &D ROOM, RECEPTION X2 )3.001,450.004,350.00 Edit Delete
325000BTU CASSETTE (QA ROOM, DIRECTOR ROOM 2 , MEETING R00M 3)3.001,380.004,140.00 Edit Delete
416000BTU CASSETTE (HOT DESK ROOM )1.001,300.001,300.00 Edit Delete
512000BTU CASSETTE (PANTRY, DIRETORS ROOM 1, DIRECTORS ROOM 3,MEETING ROOM 1, MEETING ROOM 2)5.001,250.006,250.00 Edit Delete
69000BTU CASSETTE (SERVER ROOM & DB ROOM )2.001,200.002,400.00 Edit Delete
7DUCTED UNIT 70000 BTU (RACKING AREA )2.001,900.003,800.00 Edit Delete
8TO SUPPLY LABOUR & MATERIALS TO INSTALL19.002,150.0040,850.00 Edit Delete
 NEW CHILLED WATER PIPING INCLUSIVE OF NECESSARY HANGER/SUPPORT;INSULATION;FITTINGS;CONTROL VALVE; PRESSURE GAUGE C/W GATE VALVE FOR EACH UNIT AND ACCESSORIES FOR 17UNITS CASSETTE AND 2UNITS DUCTED
9TO SUPPLY LABOUR AND MATERIALS TO INSTALL MAIN JACKETING PIPE.1.006,000.006,000.00 Edit Delete
10TO PROVIDE CHEMICAL FLUSHING AND PROVIDE WATER ANALYSIS REPORT 1.003,800.003,800.00 Edit Delete
11TO SUPPLY LABOUR AND MATERIALS TO INSTALL 1.001,700.001,700.00 Edit Delete
  CONTROL PANEL BOX FOR DUCTED 12/12 HRS AUTO SWITCH OVER
12WATER PUMP WITH INSTALLATION3.00250.00750.00 Edit Delete
13   
  
14DRAWING & PE ENDORSEMENT (OPTIONAL) $1500    Edit Delete
15REMAPKS:    Edit Delete
 1) AFTER FIRST PROGRESSIVE PAYMENT OF 70%, AIRCON ARRIVAL ABOUT 7 WORKING DAYS.
2) MATERIALS ORDER (EX:JACKETING PIPE) TAKES ABOUT 3 TO 5 WORKING DAYS.
3) WITH MATERIAL ARRIVE, JOB NEED 10 TO 15 WORKING DAYS TO COMPLETE.
4) EXCLUSION: JOB NOT STATED IN THIS QUOTATION.
Total47.00 84,640.00