						No
					 | 
					
						Product
					 | 
					
						Quantity
					 | 
					
						Unit Price
					 | 
					
						Amount
					 | 
					
						Function
					 | 
				
				| 1 | TO SUPPLY CHILLED WATER CASSETTE UNIT ONLY | 8.00 | 1,450.00 | 11,600.00 |   Edit |   Delete | 
|   | 43000BTU CASSETTE
 UNIT 0701 1 NOS; UNIT 0702 2NOS; UNIT 0703 DOWNSTAIRS 5NOS | 
| 2 | TO SUPPLY CHILLED WATER CASSETTE UNIT ONLY | 1.00 | 1,380.00 | 1,380.00 |   Edit |   Delete | 
|   | 32000BTU CASSETTE
 UNIT07-03 UPSTAIR | 
							
								| 
									3								 | 
								
									
																		  
									 	
								 | 
								
																	 | 
								
																	 | 
								
								 | 
							
							
							
								| 
								 | 
								
																	 | 
							
							
								| 
																		  
																	 | 
							
	
				| 4 | TO SUPPLY LABOUR & MATERIALS TO INSTALL | 10.00 | 1,900.00 | 19,000.00 |   Edit |   Delete | 
|   | NEW CHILLED WATER PIPING INCLUSIVE OF NECESSARY HANGER/SUPPORT;INSULATION;FITTINGS;CONTROL VALVE; PRESSURE GAUGE C/W GATE VALVE FOR EACH UNIT AND ACCESSORIES FOR 10UNIT CASSETTE UNIT | 
| 5 | INCLUDING DRAWING  | 1.00 |   |   |   Edit |   Delete | 
| 6 | WATER PUMP WITH INSTALLATION | 3.00 | 220.00 | 660.00 |   Edit |   Delete | 
| 7 | TO PROVIDE CHEMICAL FLUSHING FOR EXISTING PIPE AND PROVIDE WATER ANALYSIS REPORT PER UNIT | 3.00 | 950.00 | 2,850.00 |   Edit |   Delete | 
| 8 | REMARKS: |   |   |   |   Edit |   Delete | 
|   | 1) AFTER FIRST PROGRESSIVE PAYMENT OF 70%, AIRCON ARRIVAL ABOUT 7 WORKING DAYS.
 2) MATERIALS ORDER (EX:JACKETING PIPE) TAKES ABOUT 3 TO 5 WORKING DAYS.
 3) WITH MATERIAL ARRIVE, JOB NEED 10 TO 15 WORKING DAYS TO COMPLETE.
 4) EXCLUSION: JOB NOT STATED IN THIS QUOTATION. | 
| 9 | DISCOUNT -$740 | 1.00 |   |   |   Edit |   Delete | 
| Total | 27.00 |   | 34,750.00 |