1 | TO SUPPLY AIRCON,LABOUR AND MATERIALS TO INSTALL: | 1.00 | 30,500.00 | 30,500.00 | Edit | Delete | | BRAND: CARRIER CASSETTE UNIT
TO INSTALL NEW CHILLED WATER PIPING INCLUSIVE OF NECESSARY HANGER/SUPPORT,INSULATION,FITTINGS,CONTROL VALVE AND ACCESSORIES FOR
5NOS OF 9000BTU;
3NOS OF 16000BTU;
2NOS OF 24000BTU;
2NOS OF 32000BTU | 2 | DRAWING ONLY | 1.00 | 300.00 | 300.00 | Edit | Delete | 3 | DUCT WORKS (EST.LENGTH 25M) WITH 250X250 | 1.00 | 3,200.00 | 3,200.00 | Edit | Delete |
4 |
|
|
|
|
|
|
|
5 | REMARKS: | | | | Edit | Delete | | 1) AFTER FIRST PROGRESSIVE PAYMENT OF 70%,AIRCON ARRIVAL ABOUT 7 WORKING DAYS.
2) MATERIALS ORDER (EX:JACKETING PIPE) TAKES ABOUT 3 TO 5 WORKING DAYS.
3) WITH MATERIAL ARRIVE,JOB NEED 10 TO 15 WORKING DAYS TO COMPLETE.
4) EXCLUSION: JOB NOT STATED IN THIS QUOTATION. | Total | 3.00 | | 34,000.00 |
|